Gonzales Unified School District is excited to share the ongoing progress of the high school football stadium remodel and upgrade, a project made possible by the generous support of our community through the recent bond measures. Thanks to this collective effort, we are transforming our stadium into a modern facility that will serve students, athletes, and fans for years to come.
We will be providing regular updates on the project’s progress, including photos, videos, and key milestones. Stay tuned for exciting behind-the-scenes looks and sneak peeks as we work to bring this vision to life!
The Journey
04-15-2025
Work on the track is almost complete, with the rubber surface installed. There has been additional fencing put up around the track and walkways. The concession stand has been repainted and walkway at the top of the bleachers has been redone with concrete.
04-09-2025
Crews have started putting the orange rubber on the inner part of the track and have begun prep work for the outer portion of the track. They have also done work creating a walkway in the parking lot to get to the front entrance of the stadium. Work on the ADA seating areas has continued, with additional concrete being poured.
03-27-2025
After a few weeks of rainy weather, crews have finished the turf on the football field. The goal posts have been installed for each end zone. Work on the bleachers to improve ADA seating as well as access to the field from the bleachers. New fencing has been put up around the field and walkways.
02-25-2025
The High School logo, "Gonzales", & "Spartans" lettering has been laid out and is ready to be fully installed. The prepwork for walkway access to the visitor bleachers has started. Crews have also continued prepwork for ADA seating at the top of the bleachers near the snack bar.
02-19-2025
Crews began pouring the asphalt for the track and continue to work on the turf near the end zones.
02-18-2025
The track foundation has been prepped and is ready to have asphalt poured. The crews continue to work on the installation of the turf and work on the ADA seating area.
02-11-2025
The installation of the turf is still in progress and crews continue to work on the ADA seating area near the top of the bleachers.
02-07-2025
Crews have finished the prep on the field are starting to install the turf.
02-03-2025
Crews continue to pour concrete in areas around the field and have started work around the concession stand for ADA seating.
01-24-2025
Crews are continuing the prep work on the track and getting ready for more concrete to be poured.
01-17-2025
Concrete and railing for ADA access to the bleachers has been completed. Crews are continuing the prep work on the track and field.
12-6-2024
Crushed rock is being poured to create a sub-base that provides stability and support for the concrete ramp and other pathways to the bleachers.
11-22-2024
Concrete is being poured to construct a new ramp that will provide easier access to the bleachers. The ramp is designed to improve accessibility, ensuring that all fans can enjoy the games with greater convenience and safety.
10-24-2024
In this video, construction crews are seen preparing the ground for the new infrastructure that will modernize the stadium, including the installation of advanced technology and upgraded electrical systems. Excavators and heavy machinery are clearing the site, laying the groundwork for the new facilities that will power the stadium's future.
Pre-construction
The image captures the old football stadium before the remodel, showing its aging infrastructure and worn-out features. The bleachers, track, and field all reflect years of use, highlighting the pressing need for an upgrade to better serve our athletes and community.
Video, Photos
04-15-2025
04-09-2025
03-27-2025
02-25-2025
02-19-2025
02-18-2025
02-11-2025
02-07-2025
02-03-2025
01-24-2025
01-17-2025
12-6-2024
11-22-2024
10-24-2024
Pre-construction